This slides shows the minimum elements that a specification for silica-fume
concrete must contain.
It is far better to specify concrete performance requirements than to
specify mixture proportions. Let the concrete supplier determine the
mixture proportions to meet the needs of the project. Don't mix
prescriptive and performance elements in the same specification.
Make the contractor aware that a test placement is required. Specify that
the same equipment and finishers to be used on the actual placement are
required for the test placement.
Specify the type of finish that will be required. The exact degree of
finish can be established during the test placement.
Specify that the contractor must be prepared to protect the concrete against
plastic shrinkage cracking. Protection should roll directly over into
curing. Require submittal of a protection and curing plan.